Rural electrification: 18,452 villages are to be provided electricity in Bharat under the Deen Dayal Upadhyay Gramin Jyoti Yojana by May 1, 2018.

Created by Raahul_Kumar on 2015-12-07; known on 2018-05-02

  • Raahul_Kumar estimated 100% on 2015-12-07
  • Raahul_Kumar said “23% complete, 513 days left.http://kyrosoft.com/recpms/dashboardon 2015-12-07
  • JoshuaZ estimated 62% on 2015-12-07
  • Raahul_Kumar said “It is now 24% complete with 508 days left. 1% per 5 days means it will be completed in 385 days.on 2015-12-09
  • Raahul_Kumar said “25% 502 Days Lefton 2015-12-15
  • Raahul_Kumar said “26% 491 Days Lefton 2015-12-26
  • Raahul_Kumar said “17 days for 3% completion, at this rate will be complete in 425 days, ahead of schedule.on 2015-12-26
  • Raahul_Kumar said “27% 486 Days Lefton 2015-12-31
  • Raahul_Kumar said “28% 482 Days Lefton 2016-01-04
  • Raahul_Kumar said “At current rate of progress will only need 446 days to finish, well within schedule of 482 days.on 2016-01-04
  • Raahul_Kumar said “29% 475 Dayson 2016-01-11
  • Raahul_Kumar said “30% 469 Days Left. On track to be done by ETA.on 2016-01-17
  • Raahul_Kumar said “33% 449 Days Left.on 2016-02-06
  • Raahul_Kumar said “By my calculations based on current progress to date, should be finished 20 days ahead of schedule.on 2016-02-06
  • Raahul_Kumar said “35%438 days left.on 2016-02-17
  • Raahul_Kumar said “41%406 Days Lefton 2016-03-20